The Choctaw Lake project is finished! There was a total of 40,000 cubic yards of material removed from the lake using our VMI dredge with an 8” pump. The material was pumped up to 3,000 feet away to an open disposal basin that Heartland Dredging constructed. The dredge performed exceptionally well, and the residents are pleased with the work. Meanwhile, the 2 new jobs for the small dredges have not been completed due to permitting issues. Heartland is hopeful that it will be completed before winter hits too hard!